PROJECT UPDATE: Week of September 4, 2018

Construction Progress

Work completed since last update:

  • Completed striping and pavement markers on North and South bound lanes throughout the Project

  • Activated all traffic lights at all intersections on the Project

  • Removed all temporary traffic signal wiring and poles used on the Project

  • Progressed with landscaping work at all intersections on the Project

  • Mounted street signs on traffic signal mast arms and progressed with sign installation throughout the Project

Upcoming new work:   

  • Continue landscaping at designated intersection locations

  • Continue installing project signage

  • Install survey monuments at designated locations

  • Pull fiber optic cables through conduits on Project

  • Punch list work on Hina Lani intersection and Honokohau intersection

Upcoming work affecting traffic:

  • Punch list work at Hina Lani intersection will have an impact on the flow of traffic. A Notice to Motorists ad will be posted in the paper once work is scheduled.  Please continue checking the website for updates.

Reminder:

Queen Ka’ahumanu Highway from South of Kealakehe Parkway to North of Keahole Airport Road is still an active Construction Area with a posted regulatory speed of 35 MPH. Although the majority of construction within the travel lanes is complete, we will continue to have workers on the shoulders and in the median on the roadway every day for the next several weeks.

Please continue to help us keep motorists, bikers, pedestrians, and our workers safe by respecting the posted work zone speed limits.  

Please help to keep our roads and highways safe.