PROJECT UPDATE - WEEK OF MAY 15, 2016

Crews continue to progress south of Hina Lani St. with utility work.  Installation of waterline continues south of Ala Nui Kaloko Road.  Reclaimed water will continue at Hina Lani, along with gravity sewer, progressing south towards Honokohau Boat Harbor.   Signal interconnect conduit installation began this week near the north end of the project.

Crews will be switching over to the temporary signals and removing the existing permanent signals at the Ka'iminani intersection on Thursday, May 19.  There will be no impact to traffic as crews will be working outside the travel lanes.